In this case study article, the Moundsville Wastewater Treatment Plant in West Virginia chooses not to fix a broken blower unit, but rather to correct an outdated approach. The result is a savings of $50,000-60,000 per year in energy costs.

In this case study article, the Moundsville Wastewater Treatment Plant in West Virginia chooses not to fix a broken blower unit, but rather to correct an outdated approach. The result is a savings of $50,000-60,000 per year in energy costs.